IEC 60870-5-103 Protocol
NEW in SerialMon v3.0! Full support for IEC 60870-5-103, the companion standard for protection equipment communication.
IEC 60870-5-103 defines the informative interface between protection equipment and devices for logging/evaluation in substations. It enables communication between protection relays and substation automation systems.
Protocol Overview
IEC 60870-5-103 is specifically designed for protection equipment:
- Protection relay status and configuration
- Disturbance recording data transfer (COMTRADE)
- Protection settings readout and modification
- Measurement values from protection relays
- Event and alarm data from protection equipment
Protocol Structure
| ISO/OSI Layer | IEC 103 Layer |
|---|---|
| 7. Application layer | ASDU (Protection-specific types) |
| 6. Presentation layer | Application layer |
| 5. Session layer | |
| 4. Transport layer | Link layer (FT1.2 frame format) |
| 3. Network layer | |
| 2. Data link layer | |
| 1. Physical layer | Physical layer (RS-232/RS-485) |
ASDU Types
| Type ID | Name | Description |
|---|---|---|
| 1 | Time-tagged message | Status with time tag (24-bit) |
| 2 | Time-tagged message with relative time | Status with relative time |
| 5 | Identification | Device identification data |
| 6 | Time synchronization | Time sync command/response |
| 7 | General interrogation | Station interrogation |
| 8 | General interrogation termination | End of interrogation |
| 9 | Measurands I | Measurement set 1 |
| 10 | Generic data | Flexible data format |
| 20 | General command | Command to protection device |
| 21 | Generic command | Flexible command format |
| 23 | Disturbance data ready | Notification of available fault data |
| 26-31 | Disturbance data transfer | COMTRADE fault recording data |
SerialMon Support
Full support added in SerialMon v3.0
Operating Modes
| Mode | Description |
|---|---|
| Monitor | Passive sniffing of IEC 103 communication between protection relays and control systems |
| Master | Simulate a substation automation system polling protection relays |
| Slave/IED | Simulate a protection relay responding to master requests |
Supported Features
- All standard ASDU types for protection equipment
- General interrogation and time synchronization
- Measurement values and status indications
- Command execution
- Disturbance data notification
- Protocol validation and error detection
- Signal acceptance marking for FAT/SAT testing
- Quick command sending from tracking window
Use Cases
- Protection Commissioning - Verify protection relay communication during installation
- Troubleshooting - Debug communication issues between protection equipment and SCADA
- FAT/SAT Testing - Factory and site acceptance testing with signal verification
- Integration Testing - Test protection relay integration before go-live
- Disturbance Analysis - Monitor and capture fault recording notifications
Related Protocols
- IEC 60870-5-101 - Serial telecontrol protocol
- IEC 60870-5-104 - TCP/IP telecontrol protocol
- ABB SPA-bus - ABB protection relay communication